All Projects

NO

DATE START

DATE FINISH

DESCRIPTION

VENDOR NAME

1

18/01/2024

Â

Slope stability study requested by JMG prior going down 45m deep at Pit 1 and Pit 2

NSCI

2

25/03/2024

Â

Proposed Development of Recovery, Treatment and Disposal of Scheduled Waste (Scheduled Waste Hub) at PTD 15829, Mukim Ulu Sungai Johor, Kota Tinggi, Johor for Kitar Selatan Sdn. Bhd.

AMR

3.

13.05.2024

Â

Proposed Development of Sustainable Facility and Eco-park Centre (S.A.F.E.-T) at Lot 3670, Mukim Teluk Kalung, District of Kemaman, Terengganu for Alam Flora Environmental Solutions Sdn. Bhd. (AFES).

AMR

4.

18/01/2024

05/02/2024

Slope stability study requested by JMG prior going down 45m deep at Pit 1 and Pit 2Â

NSCI

5.

17/05/2024

Â

TO CONSTRUCT A TEMPORARY DRAIN FOR WATER RETURN FROM THE TEMPORARY POND TO THE POND 5.Â

NSCI

NO

DATE START

DATE FINISH

DESCRIPTION

VENDOR NAME

1

10/3/2023

10/3/2023

to supply manpower, tools and consumption for construction of pond c, river brooke j at NSCI Bahau.

NSCI

2

26/1/2023

14/4/2023

KERJA-KERJA PEMETAAN TERRAIN (TERRAIN MAPPING), PEMETAAN POTENSI BAHAYA (POTENTIAL HAZARD MAP), PEMETAAN GEOLOGI CERUN, DAN MENYEDIAKAN LAPORAN TEKNIKAL GEOLOGI SERTA CADANGAN TEKNIKAL.

MARYAMI SUFI HOLISTIC AND WELLNESS SPA SDN BHD

3.

24/5/2023

23/5/2023

LAPORAN CERUN FOR LOT 20001 (PIT 4)

NSCI

4.

20/4/2023

29/5/2023

GEOELECTRICAL RESISTIVITY STUDY WITH 400MM AND 200MM CABLE LENGTH. TARGET DEPTH IS APPROXIMATELY 60M AND 30M RESPECTIVELY. INTERVAL OF ELECTRODE IS 5M FOR 400M CABLE LENGTH AND 2.5M FOR 200M CABLE LENGTH.

TERAS SARI RESOURCES SDN BHD

5.

6/6/2023

22/8/2023

TO CONSTRUCT A TEMPORARY DRAIN FOR THE TEMPORARY POND TO THE POND 5.

NSCI

6.

18/8/2023

18/8/2023

DESILTING OF THE POND A, NSCI’S QUARRY.

NSCI

NO

DATE START

DATE FINISH

DESCRIPTION

VENDOR NAME

1

29/3/2022

15/5/2022

Descludging pond 5, retention pond for run off surface water for NSCI Bahau and Quarry. Curent condition pond 5 filled with silt and reduce the efficiency, washout during heavy rain

N. Sembilan cement sdn bhd

2

13/4/2022

3/6/2022

Kerja-kerja perkhidmatan penyelenggaraan telaga tiub no 1, 2 & 3 di LRA Perol.

Air kelantan sdn bhd

3.

13/4/2022

3/6/2022

Kerja-kerja perkhidmatan penyelenggaraan talaga tiub no 10, 5 & 2 di LRATG MAS.

Air kelantan sdn bhd

4.

17/4/2022

27/4/2022

THE TUBEWELL MAINTENANCE AND REHABILITATION

Air kelantan sdn bhd

5.

11/5/2022

17/7/2022

THE DESILTING AND REMOVAL OF THE SILT TO THE DESIGNATED AREA FROM THE BROOK AND JUNIOR BROOK RIVER – CONTRACT BASIS

N. Sembilan cement sdn bhd

6.

15/5/2022

17/6/2022

Supply and install of the sprinkler system at the Pati Nilai Quary Sdn Bhd

Negeri Roadstone

7.

7/7/2022

20/7/2022

TO RETRIEVE A BAILER FROM THE MW NO GW3 AND TO CARRY OUT WELL MAINTENANCE AND REHABILITATION OF THE MW NO GW7N.

Kualiti Alam Sdn Bhd

8.

28/8/2022

21/9/2022

KERJA-KERJA MEMBEKAL DAN MEMASANG SISTEM PENGAIRAN TERMASUK 1 UNIT PAM DAN 2 UNIT POLITANK (500 LITER)

Agro Resort Semuji (LKPP)

9.

5/9/2022

21/9/2022

KERJA-KERJA MEMBEKAL DAN MEMASANG SISTEM PENGAIRAN TERMASUK 1 UNIT PAM DAN 2 UNIT POLITANK (500 LITER) (Tambahan)

Agro Resort Semuji (LKPP)

10.

10/11/2022

16/11/2022

SUPPLY OF GEOTEXTILE (GEOSYNTHETICS) TO NEGERI SEMBILAN CEMENT INDUSTRIESSDN BHD – PER ROLL

N. Sembilan cement sdn bhd

11.

20/6/2022

9/1/2023

MEMBEKAL DAN MEMASANG PENUTUP ‘CONVEYER’ DI NEGERI ROADSTONE NILAI.

Negeri Roadstone

12

7/9/2022

27/1/2023

TO CONSTRUCT, SUPPLY AND INSTALL A UNIT OF WATER LEVEL INDICATOR.

NSCI

13

29/9/2022

10/3/2023

KERJA-KERJA MEMBINA PAGAR CYCLONE SEPANJANG 500M X 6’ UNTUK LADANG KAJIAN ROCK MELON DI AGRO RESORT SEMUJI.

LKPP CORPORATION SENDIRIAN BERHAD

14

25/11/2022

10/03/2023

MEMBEKAL DAN MEMASANG PINTU PAGAR LADANG BERUKURAN 12’ X 15’ DI AGRO RESORT SEMUJI (TAMBAHAN PINTU GATE)

LKPP CORPORATION SENDIRIAN BERHAD

NO

DATE START

DATE FINISH

DESCRIPTION

VENDOR NAME

1

12/01/2021

Â

LIMESTONE RESERVES INVESTIGATION USING BOREHOLES/CORE DRILLS.

NSCI

2

08/02/2021

Â

To purchase pond water level indicator for siltation Pond no.4 with installationÂ

NSCI

3.

19/03/2021

Â

Additional core drill one (1) hole is required to investigate area near the

entrance Lot 20001Â

NSCI

4.

25.03.2021

Â

Services, Civil & Reno-Civil Work  Geoelectrical Resistivity Study The purpose of this study is to detect the presence of solutions or sediments of heavy metal materials or materials resulting from

contamination consisting of metalsÂ

KUALITI ALAM SDN. BHD.